Task Report: sampleTaskPlan_20090707_c

Task Start End Duration Dependencies Assigned
0) sampleTaskPlan_20090707_c 1/6 8:00 AM 4/28 11:29 AM < 642h
1) ACME Corporation Website 1/6 8:00 AM 4/28 11:29 AM < 642h
1.1) Project Manager Allocation 1/6 9:30 AM 4/15 1:55 PM < 571.5h Project Manager {35% of 100%}
1.2) Discovery 1/6 8:00 AM 1/8 6:30 PM 24h
1.2.1) Product Requirements Definition 1/6 8:00 AM 1/8 6:30 PM 24h
1.2.1.1) Client Input/Guidelines On PRD Due 1/6 8:00 AM 1/6 8:00 AM ACME Corporation
1.2.1.2) PRD Generation 1/6 9:30 AM 1/6 6:30 PM 8h 1.2.1.1 Project Director; Producer
1.2.1.3) PRD Submission to Client 1/6 6:30 PM 1/6 6:30 PM 1.2.1.2 Almer/Blank
1.2.1.4) PRD Feedback from Client 1/8 6:30 PM 1/8 6:30 PM 1.2.1.3+16h ACME Corporation
1.2.1.5) PRD Rework 1/7 9:30 AM 1/7 2:30 PM 4h Project Director; Producer
1.2.1.6) PRD Resubmission to Client 1/7 2:30 PM 1/7 2:30 PM 1.2.1.5 Almer/Blank
1.2.1.7) PRD Initial Sign-Off from Client 1/8 2:30 PM 1/8 2:30 PM 1.2.1.6+8h ACME Corporation
1.2.1.8) Project Guide Documentation Update 1/8 2:30 PM 1/8 3:30 PM 1h 1.2.1.7 Project Director
1.3) Design 1/8 6:30 PM 3/17 6:02 PM > 383.5h 1.2.1
1.3.1) Information Design 1/8 6:30 PM 1/22 5:18 PM > 78.75h
1.3.1.1) Client Input/Guidelines On Information Design Due 1/8 6:30 PM 1/8 6:30 PM ACME Corporation
1.3.1.2) Information Design Document Creation 1/11 9:30 AM 1/13 1:42 PM < 19.25h 1.3.1.1 Project Director; Producer {25% of 100%}
1.3.1.3) Information Design Document Submitted to Client 1/13 1:42 PM 1/13 1:42 PM 1.3.1.2 Almer/Blank
1.3.1.4) Information Design Document Feedback from Client 1/19 1:42 PM 1/19 1:42 PM 1.3.1.3+32h ACME Corporation
1.3.1.5) Information Design Rework 1/19 1:42 PM 1/20 3:18 PM > 9.5h 1.3.1.4 Project Director; Producer {25% of 100%}
1.3.1.6) Information Design Resubmission to Client 1/20 3:18 PM 1/20 3:18 PM 1.3.1.5 Almer/Blank
1.3.1.7) Information Design Draft Approval from Client 1/22 3:18 PM 1/22 3:18 PM 1.3.1.6+16h ACME Corporation
1.3.1.8) Project Guide Documentation Update 1/22 3:18 PM 1/22 5:18 PM 2h 1.3.1.7 Project Director
1.3.2) Interaction Design 1/22 5:18 PM 2/15 4:09 PM > 126.75h 1.3.1
1.3.2.1) Client Input/Guidelines On Interaction Design Due 1/22 5:18 PM 1/22 5:18 PM ACME Corporation
1.3.2.2) Interaction Design Document Creation 1/22 5:18 PM 2/1 11:09 AM > 42.75h 1.3.2.1 UX Designer; Project Director {40% of 100%}
1.3.2.3) Interaction Design Document Submitted to Client 2/1 11:09 AM 2/1 11:09 AM 1.3.2.2 Almer/Blank
1.3.2.4) Interaction Design Document Feedback from Client 2/8 11:09 AM 2/8 11:09 AM 1.3.2.3+40h ACME Corporation
1.3.2.5) Information Design Document Re-work 2/8 11:09 AM 2/11 11:09 AM 24h 1.3.2.4 UX Designer
1.3.2.6) Information Design Document Redelivery to Client 2/11 11:09 AM 2/11 11:09 AM 1.3.2.5 Almer/Blank
1.3.2.7) Information Design Document Draft Approval from Client 2/15 11:09 AM 2/15 11:09 AM 1.3.2.6+16h ACME Corporation
1.3.2.8) Project Guide Documentation Update 2/15 11:09 AM 2/15 4:09 PM 4h 1.3.2.7 Project Director
1.3.3) Visual Design 2/15 4:09 PM 3/12 6:02 PM < 154h 1.3.2
1.3.3.1) Client Input/Guidelines On Visual Design Due 2/15 4:09 PM 2/15 4:09 PM ACME Corporation
1.3.3.2) Moodboard Creation 2/15 4:09 PM 2/17 2:04 PM < 14h 1.3.3.1 Producer {15% of 100%}; Visual Designer
1.3.3.3) Moodboard Delivery 2/17 2:04 PM 2/17 2:04 PM 1.3.3.2 Almer/Blank
1.3.3.4) Moodboard Selection/Feedback 2/17 2:04 PM 2/17 2:04 PM 1.3.3.3 ACME Corporation
1.3.3.5) Visual Design Creation 2/17 2:04 PM 2/27 3:00 PM < 60.5h 1.3.3.4 Producer {15% of 100%}; Visual Designer
1.3.3.6) Visual Design Submitted to Client 2/27 3:00 PM 2/27 3:00 PM 1.3.3.5 Almer/Blank
1.3.3.7) Visual Design Feedback from Client 3/5 6:30 PM 3/5 6:30 PM 1.3.3.6+40h ACME Corporation
1.3.3.8) Visual Design Re-work 3/6 9:30 AM 3/10 3:22 PM > 20.75h 1.3.3.7 Producer {15% of 100%}; Visual Designer
1.3.3.9) Visual Design Redelivery to Client 3/10 3:22 PM 3/10 3:22 PM 1.3.3.8 Almer/Blank
1.3.3.10) Visual Design Draft Approval from Client 3/12 3:22 PM 3/12 3:22 PM 1.3.3.9+16h ACME Corporation
1.3.3.11) Project Guide Documentation Update 3/12 3:22 PM 3/12 6:02 PM < 2.75h 1.3.3.10 Project Director; Producer {50% of 100%}
1.3.4) Final Design Documentation to Client 3/12 6:02 PM 3/12 6:02 PM 1.3.1, 1.3.2, 1.3.3 Almer/Blank
1.3.5) Final Design Deliverables Sign-Off from Client 3/17 6:02 PM 3/17 6:02 PM 1.3.4+24h ACME Corporation
1.4) Software Design 2/15 4:09 PM 3/11 11:09 AM 140h 1.3.2
1.4.1) Client Input/Guidelines On Software Design Due 2/15 4:09 PM 2/15 4:09 PM ACME Corporation
1.4.2) Software Design 2/15 4:09 PM 3/4 11:09 AM 100h Software Architect
1.4.3) Software Design Submitted to Client 2/15 4:09 PM 2/15 4:09 PM Almer/Blank
1.4.4) Software Design Feedback from Client 2/19 4:09 PM 2/19 4:09 PM 1.4.3+32h ACME Corporation
1.4.5) Software Design Re-work 3/4 11:09 AM 3/9 11:09 AM 24h 1.4.4
1.4.5.1) Software Architecture Re-work 3/4 11:09 AM 3/9 11:09 AM 24h Software Architect
1.4.6) Software Design Redelivery to Client 3/9 11:09 AM 3/9 11:09 AM 1.4.5 Almer/Blank
1.4.7) Software Design Draft Approval from Client 3/11 11:09 AM 3/11 11:09 AM 1.4.6+16h ACME Corporation
1.5) Engineering 3/11 11:09 AM 4/28 11:29 AM > 272.25h 1.4
1.5.1) Beta Assets Received from Client 3/11 11:09 AM 3/11 11:09 AM 1.5.2SS ACME Corporation
1.5.2) Beta 3/11 11:09 AM 4/5 4:09 PM 140h
1.5.2.1) Beta Test Plan Generation 3/12 6:02 PM 3/16 2:02 PM 12h Project Director
1.5.2.2) Engineering 3/11 11:09 AM 3/29 4:09 PM 100h Developer
1.5.2.3) Internal Beta QA 3/16 2:02 PM 3/19 2:02 PM 24h 1.5.2.1 QA
1.5.2.4) Beta Engineering Re-work from Internal QA 3/29 4:09 PM 4/5 4:09 PM 40h 1.5.2.3 Developer
1.5.2.5) Beta Launch 3/19 2:02 PM 4/2 4:29 PM < 82.5h 1.5.2.3
1.5.2.5.1) Initial Beta Delivery 3/19 2:02 PM 3/19 2:02 PM Almer/Blank
1.5.2.5.2) Client Feedback on Beta 3/26 2:02 PM 3/26 2:02 PM 1.5.2.5.1+40h ACME Corporation
1.5.2.5.3) Beta Re-engineering 4/1 11:09 AM 4/2 11:09 AM 8h 1.5.2.5.2 Software Architect; Developer
1.5.2.5.4) Beta Re-delivery 4/2 11:09 AM 4/2 11:09 AM 1.5.2.5.3 Almer/Blank
1.5.2.5.5) Client Approval of Beta 3/19 2:02 PM 3/19 2:02 PM ACME Corporation
1.5.2.5.6) Beta Push 4/1 5:29 PM 4/2 4:29 PM 7h Software Architect; Developer
1.5.2.5.7) Beta Completion 3/19 2:02 PM 3/19 2:02 PM Almer/Blank
1.5.3) Lump Feedback on Beta Due from Client 4/9 4:29 PM 4/9 4:29 PM 1.5.2.5+40h ACME Corporation
1.5.4) Final Release Assets Received from Client 4/9 4:29 PM 4/9 4:29 PM 1.5.5SS ACME Corporation
1.5.5) Final Release 4/9 4:29 PM 4/28 11:29 AM 100h 1.5.3
1.5.5.1) Final Release Test Plan Generation 4/9 4:29 PM 4/13 11:29 AM 12h Project Director
1.5.5.2) Engineering 4/9 4:29 PM 4/21 11:29 AM 60h Developer
1.5.5.3) Internal Final Release QA 4/13 11:29 AM 4/19 11:29 AM 32h 1.5.5.1 QA
1.5.5.4) Final Release Engineering Re-work 4/21 11:29 AM 4/27 11:29 AM 32h 1.5.5.3 Developer
1.5.5.5) Final Delivery 4/27 11:29 AM 4/28 11:29 AM 8h 1.5.5.4
1.5.5.5.1) Client Approval of Delivery 4/27 11:29 AM 4/27 11:29 AM ACME Corporation
1.5.5.5.2) Push 4/27 11:29 AM 4/28 11:29 AM 8h Software Architect; Developer
1.5.5.5.3) Project Completion 4/27 11:29 AM 4/27 11:29 AM Almer/Blank